Hardie board installation will require joints between planks.
How to put up hardie siding.
Caulking joints are unnecessary but flashing behind the joints is required.
Learn how to install hardiepanel vertical siding products.
The top post will go across the two vertical blocks that will extend them to the bottom side of the trim.
Leave a small gap at butt joints and fill with caulk.
Colorplus touch up kits can be used to cover nicks scrapes and nail holes that may occur over time.
When taking planks from the pallet for installation avoid repeating the texture pattern by working your way across.
If hand nailing fiber cement siding use hot dipped galvanized nails and drive the nails into the wall studs.
For accurate fastening snap vertical chalk lines on the water resistive barrier at the center of every stud location.
Well many edmonton siding contractors forget to cover their hardie with tarps when they pack up for the night.
Begin at the lowest point at the side of your house where you will install your hardie siding.
Blind nail your hardie siding in place.
Cut a piece of 6 inch wide steel coil trim about 1 inch longer than the width of a siding board and place it behind the joint.
How to install hardie siding step 1.
If the touch up area is larger than the size of a dime the use of colorplus touch up kit is not recommended.
Hardie siding does a great job of wicking moisture when it is installed on the wall but when it s uncovered and flat on the ground it will absorb water.
Do not in fill landscaping up to the siding.
Leave a gap of approximately 1 4 between your window and the hardie plank so any leaking water behind the siding has the scope of getting out.
Re painting siding colorplus products.
It s rot proof insect proof fireproof and a perfect solution f.
Be sure the flashing overlaps the siding course below.
Install shims to build out wall even with window flange.
Install flashing at all end joints where two pieces of siding butt together.
Apply a 1 1 4 inch starter strip right above the water table trim located at the bottom edge of the house wall.
This video will outline the basics of installing james hardie s fiber cement products.
Join factory edges and place the cut edges against the corner trim boards.